Import project data from database

DB tool > Functions tab > Functions group >  Import menu > Import from another project
DB tool > Management tab > Import group > Import to shared database

With these functions, you can import project data (devices, cables, heaters, I/Os, circuits, etc.) from other projects (EDBProject.sqlite/EDBProject.mdb).

  • Only new rows – Already existing information will not be imported again.

  • Import deleted – Devices etc. defined as To be deleted will also be imported.

Additional information

  • When the target device already exists and has product data: If the device to import has the To be deleted option enabled but the target device does not, product data/pin/plate etc. information will not be replaced.

  • If the target object already exists and neither one (import/target) has the To be deleted option enabled:

    • If the target object already has product data, product data will not be imported.

    • If the target object already has pins, pins will not be imported.

    • Plates, additional information, etc. are handled the same way.

  • If the target device/location/circuit/cable has the To be deleted option enabled and the object to import has it disabled:

    • Object information will be replaced.

    • Product data will be replaced.

    • Pins will be replaced.

    • Plates will be replaced.

    • Additional information will be replaced.

    • The To be deleted option will be disabled.