Route more instrument lines

Route a new instrument line (in the same way as earlier) from the lower quadrant of the instrumentation symbol to the actuator of the valve below the vessel.

Route the third instrument line from the rightmost quadrant point of the instrumentation symbol to the left silhouette line of the vessel, i.e. to the level sensor. Connect the end of the line to the vessel using command New Connection Point, at this point there is no automatic connection.

The instrumentation symbols are set up in this configuration so that there are four nodes accessible at quadrants: up, down, right, and left.

When the symbol is horizontally stretched and you want to connect the instrument line to the right or left side of the symbol you must make new connection points since the locations of nodes do not stretch with the symbol or you can connect to the existing connection points which are a little bit inside the stretched bubble.